Project Status Day 9 : Monday 06/02/12

What has been done:

  • Finalized the control interface.
  • Finished editing the sounds in Kyma X.
  • Done the final test and adjustments.
  • Made the presentation and slides.

What will be done tomorrow:

  • Installation of the materials at iMAL.
  • Presentation rehearsal.

Problems & questions:

  • None.

Project Status Day 7 : Saturday 04/02/12

What has been done:

  • A working control interface.
  • Adjusting the sensors and Skemmi to interact with the control interface (via OSC messages).
  • Working Skemmi to interact with Kyma X (via OSC messages).
  • Analyzing/creating the sounds in Kyma X.
  • Testing the control interface with Processing.

What will be done tomorrow:

  • Finish editing the sounds in Kyma X.
  • Finish the final control interface.
  • Do the final test and adjustments.
  • Make the presentation and slides.

Problems & questions:

  • Problem with the resolution.

Project Status Day 6 : Friday 03/02/12

What has been done:

  • Working on Skemmi to send OSC messages.
  • Analyzing/creating the sounds in Kyma X.
  • Testing the control interface with Processing.

What will be done tomorrow:

  • Editing the sounds in Kyma X.
  • Work on Skemmi to interact with Kyma X.
  • Finish the control interface.
  • Do the final test and adjustment.

Problems & questions:

  • Problem with OSC message type.

Brussenses Poster

 

Yesterday we worked as well on the project poster which will be presented on febuary 07/2012 together with our interactive sound-installation. It contains a project description as well as the sensors we are going to use and the work-around of the different components.

You can see the poster large-scaled on our project-side.

Project Status Day 5 : Thursday 02/02/12

What has been done:

  • Getting signals from the sensors.
  • Working on Skemmi to process the signals and to send OSC messages.
  • Analyzing/creating the sounds in Kyma X.
  • Making the poster.
  • Adding the “offline mode” (AKA MP3 player) for the internet radio stream program.
  • Testing the control interface with Processing.

What will be done tomorrow:

  • Editing the sounds in Kyma X.
  • Test the sensors and choose which parameters to use.
  • Work on Skemmi to interact with Kyma X.
  • Make the control interface.

Problems & questions:

  • Problem with the fluidity of the gyroscope.

Project Status Day 4 : Wednesday 01/02/12

What has been done:

  • Testing the sensors and getting signals from its.
  • Working on Skemmi to process the signals.
  • Recording sounds and taking pictures/videos of Brussels (part1).
  • Testing/analyzing/creating the sounds in Kyma X.
  • Catching an internet radio stream, analyzing it’s frequency and sending OSC messages based on it with Pure Data.

What will be done tomorrow:

  • Create the sounds in Kyma X.
  • Test the sensors and getting signals from its.
  • Work on Skemmi to process the signals and to send OSC messages.
  • Make the poster.

Problems & questions:

  • Problem with the serial port.
  • Problem with the stability of the gyroscope